Bronson Ave construction staging and schedule

– Contract Awarded to Colautti construction Ltd.
– Anticipated Construction Start – Mid March 2012.

2012 Construction

– Arlington to Maclaren – Full Reconstruction
. Bronson Closed – Catherine to Somerset
. Local vehicle access maintained via side street access
. Pedestrian access to residences maintained
. No 0n-street parking permitted

– Gladstone (Bronson to Cambridge) – sewer relocation
. Lane reductions
. No on-street parking pemitted in construction zone

2013 Construction

– Arlington to Gladstone – Full 4 Lane Arterial operations
. Minor lane reductions required for final asphalt and crosswalk construction

. Gladstone to Somerset – lane reductions ( March to June 2013)
. Sidewalk, landscape/streetscape, final asphalt and crosswalk construction
. Full 4-Lane Arterial operations after June 2013

– Somerset to Laurier – Full reconstruction
. Bronson Closed – Somerset to Laurier
. Local vehicle access maintained via side street access
. Pedestrian access to residencess maintained
. No on-street parking permitted

Bronson construction to be completed Sep 2013

Sidestreet construction (Christie, Florence, Laurier) to be completed Dec 2013