Bronson Ave construction staging and schedule
– Contract Awarded to Colautti construction Ltd.
– Anticipated Construction Start – Mid March 2012.
2012 Construction
– Arlington to Maclaren – Full Reconstruction
. Bronson Closed – Catherine to Somerset
. Local vehicle access maintained via side street access
. Pedestrian access to residences maintained
. No 0n-street parking permitted
– Gladstone (Bronson to Cambridge) – sewer relocation
. Lane reductions
. No on-street parking pemitted in construction zone
2013 Construction
– Arlington to Gladstone – Full 4 Lane Arterial operations
. Minor lane reductions required for final asphalt and crosswalk construction
. Gladstone to Somerset – lane reductions ( March to June 2013)
. Sidewalk, landscape/streetscape, final asphalt and crosswalk construction
. Full 4-Lane Arterial operations after June 2013
– Somerset to Laurier – Full reconstruction
. Bronson Closed – Somerset to Laurier
. Local vehicle access maintained via side street access
. Pedestrian access to residencess maintained
. No on-street parking permitted
Bronson construction to be completed Sep 2013
Sidestreet construction (Christie, Florence, Laurier) to be completed Dec 2013
If you have any questions and comments about this issue, please contact
Bruce Kenny at 613-580-2424 * 20128, email: bruce.kenny@ottawa.ca
Diane Holmes at 613-580-2484